Abstract 
Before reconstruction can begin after a natural disaster, temporary
              housing is essential to stabilization of a community.  The
              offsite, rapid construction, and the ability to transport (and
              relocate) are two advantages of the ruggedized manufactured home.  Two
              improved specifications, EnergyStar (ES) and
              the Building America Structural Insulated Panel (BASIP)
              manufactured home, are suggested in this paper that enhance the
              energy efficiency, sustainability, and indoor air quality and provide
              back up power, without compromising human health, safety or comfort.  The
              energy performance of the ES and BASIP manufactured
              homes are compared to the base case or currently specified ruggedized
              manufactured home using the FSEC developed ENERGYGAUGE®  USA
              (Version 2.5.9) software.  The specifications presented in
              this paper allow for better quality construction and includes renewable
              energy. This not only reduces utility bills during regular operations
              but provides electricity and hot water for essential functions
              during power outages associated with reconstruction following a
              natural disaster. 
Introduction 
Hurricane Katrina caused major devastation
              to parishes, communities and entire cities requiring accommodations
              of mass quantities and extreme urgency.  The Federal Emergency Management Agency (FEMA) responded
              to the temporary housing needs by procuring over 100,000 travel trailers and
              over 25,000 ruggedized manufactured homes.  However, finding the proper
              location and the costs associated with constructing, transporting, installing,
              maintaining and operating these temporary housing accommodations has become controversial.  Local
              governments denied installments within flood zones (which are where most of the
              destruction and devastation occurred and where the temporary housing was needed)
              and local citizens brought opposition citing that they feared these “FEMA
              Cities” would increase crime rates and lower their property values.   Critics
              believe that dispersing the money they spent per home, directly to each of the
              victims they provided accommodations to, is a better use of taxpayer dollars
              than purchasing these units for temporary and often, one time only, use.  While
              the temporary housing program is antiquated, it is what the law
              allows. 
FEMA procured manufactured
              homes are used to accommodate victims of natural disasters.  As
              hurricanes are predicted to intensify and increase in numbers,
              more temporary structures will be needed.  When Hurricane
              Katrina struck the shores of Louisiana, Mississippi and Alabama
              last year, 25,000 manufactured homes and 100,000 travel trailers
              were ordered (and built) to help accommodate the thousands of victims
              who could not find and/or afford safe housing while their homes
              were being repaired or in some cases, rebuilt completely.  By
              extrapolating information from recent articles, the costs associated
              with recent manufactured home and travel trailer purchases amounts
              to approximately 2.9 billion dollars.   Each travel trailer
              costs about $10,000.  Each manufactured home costs about $76,800
              per dwelling, which includes purchase, transportation, installation,
              maintenance, cleaning and disposal.  However, these figures
              do not include energy costs and environmental impacts, associated
              with the manufactured homes that are currently used. 
Continued to be scrutinized for temporary home expenditures,
            FEMA is complying  with what
            law allows.  The
            Stafford Act limits the amount of money FEMA can grant
            directly to an individual at $26,200. While
            this may seem like adequate funds to support a household
            for a period of 18 months, some times, as experienced
            during Hurricane Katrina, safe housing accommodations
            are not available because an entire community has been
            devastated.   The program for providing ruggedized
                          manufactured homes was developed in the 70’s
            and although antiquated, the
            program or procurement specifications warrant improvement.  
Manufactured homes, utility expenses, maintenance,
            etc. are provided at no cost to the victims until they
            can move back into their existing homes or find other
            permanent housing.  The
            manufactured homes are typically provided for a period of not more
            than 18 months. Once the 18 month period has expired, the manufactured
            homes are vacated and immediately transported to a staging area for
            future reuse or sale through the GAS website (http://gsaauctions.gov/gsaauctions/gsaauctions).  If
            displaced residents can not find affordable housing, extensions are
            granted by FEMA.  Most recently, the Punta Gorda, FL village
            has extended the remaining occupants’  stay until September
            2006, totaling a 24 month housing period for these residents.  In
            Florida there are 4,160 manufactured homes or trailers still occupied
            by storm victims, down from a 2004 peak of more than 17,000. There
            were 551 families at one time in the Punta Gorda village that opened
            in November 2004 (see photo of typical FEMA temporary community,
            the one pictured in Figure 1 is in Arcadia, FL).    
The procurement process that FEMA initiates when manufactured
               home orders are needed, start with FEMA requesting
            quotes
            from manufactured home builders to build the homes
            in accordance with HUD Manufacturing Housing
            Standards,
            also known as Title 24 (Chasar, et al. 2004). The
            manufactured homes specified to these standards,
            developed
            in the 70’s,
            are often constructed to the minimum standards, resulting in large
            energy use compared to their site built equivalents.  The specifications
            recently used in hot and humid climates (i.e. areas where Hurricane
            Katrina struck) have the potential for indoor air quality and high
            maintenance concerns, in addition to high energy use.   Poor
            indoor air quality can induce medical complications in occupants
            with asthma or other chronic illnesses and with energy costs on the
            rise, procurement specifications necessitate energy efficient solutions
            without compensating human comfort or safety.  
If FEMA’s current
              procurement process is to remain standard procedure, this report
              recommends two specifications for consideration.   The EnergyStar Ruggedized
              Manufactured Home (ES) and the Building America Structural
              Insulated Panel Manufactured Home (BASIP) specifications,
              included in this report, provide improved temporary shelter accommodations
              suitable for multiple moves, and have capabilities to provide power
              for essential loads during extended power outages.  Not only
              are the tangible benefits associated with energy cost savings the
              justification for this report, but indoor air quality plays and
              increasingly demanding role amongst occupants with sensitivities
              to asthma and other environmental related health conditions.   Also
              included in this report are energy cost comparisons and analysis.   
  
Figure 1. FEMA City, Arcadia, FL 
              Photo Credit: FEMA             
The ES manufactured home specification is modeled from
              the Energy Star guidelines for manufactured homes (MHRA 2003).  An
              ENERGY STAR labeled manufactured home must be at least 30% more
              energy efficient in its heating, cooling and water heating than
              a comparable home built to the 1993 Model Energy Code (MEC) (Chasar,
              et al 2004).  
The
            specification
            for BASIP goes
            a little further in creating a
            specification that results in optimal indoor air quality, increased
            energy savings and also provides  “free
            energy”.  Table
            1 summarizes the window,
            and surface U values as well as other characteristics.  
Table 1.  Summary of Construction
            of the Existing and Proposed  
            Specifications for FEMA
            Ruggedized
            Manufactured Homes 
| Characteristic   | 
Base Home
                  (existing)  | 
Energy
                  Star (proposed)  | 
BASIP
                  (proposed)  | 
 
Floor Insulation  | 
R-19  | 
R-21  | 
R-19  | 
 
Wall Insulation  | 
R-13  | 
R-13.5  | 
>R-15.4  | 
 
Ceiling Insulation  | 
R-21  | 
R-18.5 roof deck
                    radiant barrier  | 
>R-23  | 
 
Roof  | 
Dark Shingle  | 
Light shingle
                    with radiant barrier  | 
White metal raised
                    seam roof  | 
 
Windows  | 
Single Pane, Metal
                    Frame  | 
Low-E Vinyl; Frame  | 
Low-E Vinyl Framed
                    with storm shutters  | 
 
Heating System  | 
Electric Resistance
                    Furnace, COP:1  | 
Heat Pump HSPF
                    7.5  | 
Heat Pump HSPF
                    7.7  | 
 
Cooling System  | 
Central Air (Split
                    System) Conditioning SEER13-2 ton  | 
Wall Hung Heat
                    Pump SEER 13-2 ton  | 
Wall Hung Heat
                    Pump SEER 13-1.5 ton  | 
 
Water Heater  | 
Electric Water
                    Heater 40 gallon capacity  | 
Electric Water
                    Heater 40 gallon capacity  | 
ICS Solar Water
                    Heater with backup 40 gallon electric water heater  | 
 
Ventilation System  | 
Under floor  | 
Above ceiling
                    in vented attic  | 
Under SIP roof
                    ( in conditioned space, unvented attic)  | 
 
Duct Joints (leakage expressed
                    as CFM25 to out as % of floor area)  | 
Industry Standard – 6%
                    leakage to out  | 
Sealed with mastic – 3%
                    leakage to out  | 
Sealed with mastic
                    (inside thermal envelope) 0% leakage  | 
 
House air tightness (in terms
                    of ACH50)*  | 
7.5  | 
5.10  | 
4.00  | 
 
Retractable Awning  | 
N/A  | 
Optional (provides
                    additional square footage/outdoor space)  | 
Optional (provides
                    additional square footage/outdoor space)  | 
 
On Site Generated Power  | 
N/A  | 
N/A  | 
3.25kW PV system  | 
 
 
*Figures
                from measured data of blower door test of US manufactured housing
                (Baechler, et al, 2002) 
Base Case,
                Energy Star and Building America Structural Insulated
                Panel Manufactured Home Characteristics 
Improving the construction methods
              and energy efficiency of federally procured ruggedized manufactured
              homes, used as temporary accommodations, will increase the durability
              and expand the life expectancy and reusability.  The improved
              specifications and revised roof layout of the BASIP will
              also accommodate a mating of “single
              wide” units to make a “double wide” and larger
              unit that would provide a more comfortable environment and a more
              mainstream approach to typical home floor plans (see end wall elevations
              as illustrated in Figure 3).  This
              report does not explore floor plan redesign at this time; however
              it does identify some of the few designs that have evolved since
              Hurricane Katrina left so many victims homeless.   
The base case or currently
              procured and the proposed ES ruggedized manufactured home
              have overall dimensions of 14’x 60’ (Figure 2).  The
              units specified have 3 bedrooms and 2 baths. The base case and ES units
              have ventilated attics and gabled roof plans (Figure 3).  The BASIP unit
              has been lengthened to
              accommodate a mechanical room and mono-sloped roof (Figures 4 & 5).   
The ES specification
                uses an advanced framing method.  While the base case uses
                typical 2x4 stud construction spaced on 16” centers, the
                advanced framing method uses 2x6 studs spaced on 24” centers.  Advanced
                framing methods may reduce wood use up to 25% and improve wall
                thermal resistance values from 5 to 10%.  It can also decrease
                labor with fewer pieces going together, therefore saving
                money.  The BASIP specification
                uses structural insulated panel method with integral wire chases
                for walls and the roof but the floor system uses advanced framing
                method, locating the plumbing requirements in the “belly”,
                as does the base case and ES. 
The BASIP specifies
                a photovoltaic (pv) integrated metal roof system with a skylight
                and Integrated Collector Storage (ICS) solar hot water system.  The
                elevations illustrate “Bahama” style shutters that
                provide hurricane protection and solar shading.  The end
                wall elevation (Figure 5) illustrates the inclusion of a retractable
                awning that also provides solar shading and additional square
                footage. 
Energy
                  Analysis Using EnergyGauge® 
 The proposed specifications and
              the base case federally procured manufactured home are analyzed
              using the FSEC developed ENERGYGAUGE® USA (Version 2.5.9) software program.
              This program predicts building energy consumption using the DOE2
              analysis engine with a user friendly front end that develops DOE2
              input files and models that are more appropriate for residential
              building systems (Parker, et. al, 1999).   
An analytical model
              was developed for each of the manufactured home specifications.  These
              models were essentially the same with differences only in the R-values
              in the various building envelope components, the duct leakage values,
              the heating and cooling equipment, fenestration properties and
              the integration of renewable energy sources, i.e. pv and solar
              hot water heating.  The
              base case and ES are similar in geometry but differ in
              hvac systems engineering and hvac equipment location.   
Considering the energy
              costs alone, these specification recommendations facilitate significant
              utility demand reductions.   During a 12 month period, the
              latest order of 25,000 FEMA specified ruggedized manufactured homes
              will consume about 250 GWh, which will cost the Federal Government
              approximately 32.55 million dollars (at $0.13/kWh).  If these
              units were deployed to other areas like Hawaii, where utility rates
              are almost 44% higher, the government’s electric bill could
              cost over 46 million dollars.  The ES, which proposes
              to improve the energy efficiency by at least 14%, would provide
              a savings of over 4.5 million dollars over a 12 month period.  The BASIP, proposes
              to improve the efficiency by at least 78% (see Table 2).  This
              equates to about 19.5 GWh of electricity saving approximately 25.4
              million dollars.    
The ES manufactured
              home would eliminate approximately 23,500 tons of greenhouse gas
              emissions, equivalent to removing 3,815 passenger cars and light
              trucks from the highway for one year or saving our reliance on
              49,595 barrels of oil.  The BASIP specification would
              remove approximately 119,000 tons of greenhouse gas emissions,
              equivalent to removing 19,318 passenger cars and light trucks from
              the highway for one year or saving our reliance on 251,134 barrels
              of oil. 
Table 2.  Summary of Comparisons of Simulated
              Savings 
End-Use  | 
Base 
(existing)  | 
Energy
                      Star 
(proposed)  | 
% Savings 
Over Base  | 
BASIP 
(proposed)  | 
% Savings 
Over Base  | 
 
Annual Energy Use (kWh)  | 
10,017  | 
8,622  | 
14  | 
*2,189 
                  (6,161 total)  | 
78  | 
 
Annual Energy Costs ($) @ $0.13/kWh  | 
1,302  | 
1,122  | 
14  | 
286  | 
78  | 
 
Annual CO2 Output 
                  (tons)  | 
5.85  | 
4.91  | 
16  | 
1.09  | 
81  | 
 
AC  | 
2,181  | 
1,652  | 
24  | 
1,458  | 
33  | 
 
Heat  | 
1,316  | 
373  | 
72  | 
487  | 
63  | 
 
Hot Water  | 
2,768  | 
2,652  | 
4  | 
**1,346  | 
51  | 
 
Lighting  | 
1,111  | 
1,111  | 
0  | 
479  | 
57  | 
 
 
* Net Energy Usage = Total Energy Usage – PV Produced (see
              Figure 7 for details) 
** This figure differs from figure in Appendix B (page B12) to include additional
energy  
usage during the freeze protection months of December, January and February) 
  
Figure 2. Floor plan for
              the Base Case (Courtesy of Palm Harbor Homes) 
 
  
  
Figure
              3. Elevations for the Base Case (Courtesy of Palm Harbor Homes) 
 
  
Figure
              4. Floor plan (by Palm Harbor Homes, et al.) for the Energy Star
              &  
              Building America Structurally Insulated Panel Manufactured Homes  
 
  
  
Figure
              5. Elevations for the Building America  
              Structurally 
              Insulated Panel
              Manufactured Home  
Inegrated PV Array 
The BASIP specification
              proposes the integration of a 3.25kWp pv array that would generate
              the peak power requirements.  This is especially beneficial
              when manufactured homes need to be deployed to areas where utilities
              have not been restored or during times when service is interrupted.    EnergyGauge®  models
              the annual energy use and the annual energy produced by the pv
              array for the home located in New Orleans, LA.   Figure 6
              illustrates the summary of monthly averages and Figure 7 illustrates
              the summary of hourly averages.   The pv array produces a
              net energy of 4,224 kWh.  Total consumption is 6,413 kWh annually
              for a net energy use of 2,189 kWh and 78% savings.   If the
              pv array was omitted, the BASIP would produce 38% savings over
              the base case manufactured home. 
 | 
 | 
 
Figure 6. Monthly electrical  
                  consumption and production.  | 
Figure 7. Hourly
                  summary of electrical  
                  consumption and production   | 
 
 
Figure 8 demonstrates the average hourly electrical uses for the
              whole year, revealing the hvac and hot water require the largest
              demand (which is also typical in the base case and ES models). 
  
Figure 8. BASIP manufactured home 
              electrical end uses. 
HVAC 
 The
                base case manufactured home as it is constructed today uses a
                mechanical system that is ducted under the floor of the home
                (referred to as “in the belly”).  The air handling
                equipment is in the interior of the home and the compressor is
                set onto a concrete pad once the manufactured home is delivered
                to the site.  This requires coordination and additional
                personnel to connect the system on site and also almost never
                involves any commissioning or verification that the system is
                functioning properly as designed.  The ES manufactured
                home models an improved hvac system with higher energy efficiency
                and improved requirements on duct sealing.   It also relocates
                the ductwork above the ceiling, as does the BASIP.   However,
                the BASIP creates a conditioned space for the ductwork
                due to the sip system.  The relocation of ductwork above
                the ceiling eliminates the risk of supply vents being covered
                with furniture.  The BASIP uses the plenum above
                the ceiling and below the sip for return air supply (see Figure
                9).  This may create an example where innovative technology
                precedes code development because flame spread ratings and fire
                code issues may need to be investigated further to ensure code
                compliance. 
The BASIP specification
              proposes a hvac system that is installed onto the home in the factory,
              allowing the mechanical system to be completely operational upon
              delivery.  The BASIP also properly sizes the unit
              with respect to its characteristics, allowing proper humidity removal
              and better indoor air quality. 
 The energy savings
              from the improved air conditioning and heating demands amount to
              44% and 45% for the ES and BASIP respectively
              over the base case.  The BASIP can credit this savings
              so the increased energy efficient rating and the properly sizing
              of the system.   The SIP, in addition to tight ducts, results
              in tighter construction, less leakage and better indoor air quality. 
Domestic
              Hot Water 
The BASIP manufactured
              home specifies an Integral Collector Storage (ICS) hot water system
              which saves about 50% energy over the base case and ES home
              (see Figure 10).  In the ICS, the hot water storage system
              is the collector. Cold water flows progressively through the collector
              where it is heated by the sun. Hot water is drawn from the top,
              which is the hottest, and replacement water flows into the bottom.
              This system is simple because pumps and controllers are not required.
              On demand, cold water from the house flows into the collector and
              hot water from the collector flows to a standard hot water auxiliary
              tank within the house (Harrison, et. al, 1997).  The benefit
              to using an ICS system over a drain back system is less mechanical
              parts and pumps.  The BASIP unit
              will have a user’s manual and diagrams installed at the water
              heating system (located in the mechanical room, see Figure 3) that
              indicate freeze protection procedures during the months of December,
              January and February, as well as during transportation and relocation.   Another
              benefit of using an ICS system is the availability of hot water
              during power outages.  
  
  
Figure 9. BASIP cross section and HVAC Layout  
 
  
Peliminary Economics 
 Early in the research
              of this report, incremental cost estimates were generated for the ES manufactured
              home of about $900.  However, due to the proposed wall mount
              hvac system, third party mechanical system installation costs are
              omitted (and for each relocation).  These
              charges are estimated at $700 per move.  Table 4 estimates
              incremental costs per component and assumes two moves.  This
              results in a net savings of approximately $854 over the base case,
              including other proposed upgrades.  The
              proposed BASIP manufactured
              home specifications have incremental costs associated with the
              skylight, pv, solar hot water system, high efficiency hvac system
              and sip construction.  The
              pv array is a large incremental cost in the BASIP manufactured
              home specification.   Systems can generally costs about $10K
              per kW of pv array.  This
              would amount to approximately $32.5k for the specified BASIP system.
              Optimistically and with bulk pricing for many of these systems
              purchased, the array could be procured as low as $6 per kW or about
              $20k (the figured used in Table 3).   Another
              large incremental costing component is the ICS hot water system.  This
              is estimated at a $2,300 up charge from the typical electric water
              heaters, which cost about $200.  The other incremental costs
              in Table 4 are likely much higher than would be actually realized
              due to the experimental nature of the proposal.  With these
              caveats understood, Table 4 illustrates the incremental costs,
              energy savings and simple payback periods for each specification.  The
              life cycle costs will be determined at a later date if the scope
              of this project warrants such investigation.  Note that the
              savings and paybacks will vary in accordance with the home’s
              location in respect to the utility rates. 
Table 3.  Incremental Costs Comparisons
              and Savings 
   | 
Incremental 
Cost  | 
Incremental 
Cost 
($/ft2)   | 
Electric 
Rate 
($)  | 
Energy 
Savings 
(kWh/day)  | 
Annual
                      Energy Savings 
($)  | 
Simple 
Payback 
(yrs)  | 
Annual
                  Life Cycle Costs/yr  | 
 
ES Home  | 
($854)  | 
($1.04)  | 
$0.13/kwh  | 
$4.27  | 
$201  | 
-  | 
$3,670  | 
 
BASIP Home  | 
$27,301  | 
$29.55  | 
$0.13/kwh  | 
$21.59  | 
$1,023  | 
27  | 
$3,649  | 
 
 
 
Table 4.  Component/Incremental Cost Estimates
              for ES & BASIP 
    | 
ES Home
                      Component  | 
ES Home
                      Component 
Cost Increment  | 
BASIP Home 
Component   | 
BASIP Home
                      Component 
Cost Increment   | 
 
HVAC (equipment)  | 
Wall hung AC/HP,
                    SEER 13  | 
$101  | 
Wall hung AC/HP,
                    SEER 13  | 
$101  | 
 
HVAC Labor (based on
                      2 moves)  | 
Negative cost due
                    to equipment attached to unit  | 
($1,400)  | 
Negative cost
                    due to equipment attached to unit  | 
($1,400)  | 
 
Framing  | 
Advanced framing,
                    less material, less labor  | 
$0  | 
Sip (walls & roof) ±$3.25
                    square foot  | 
$2000  | 
 
Windows  | 
Vinyl frame, dbl.
                    pane, low-e  | 
$400  | 
Vinyl frame, dbl.
                    pane, low-e  | 
$400  | 
 
Roof  | 
Light colored asphalt
                    shingle  | 
$0  | 
White, raised
                    seam, metal roof  | 
$2,200  | 
 
Floor Plan  | 
N/A  | 
N/A  | 
Lengthened floor
                    plan  | 
$700  | 
 
Jump Duct  | 
Jump duct for return
                    air from wall hung at end of unit  | 
$45  | 
n/a  | 
n/a  | 
 
Retractable awning  | 
Optional  | 
N/A  | 
12’w x 10’d  | 
$300  | 
 
Bahama shutters  | 
N/A  | 
N/A  | 
See figure 4  | 
$400  | 
 
Skylight  | 
N/A  | 
N/A  | 
(1) skylight 18sq.ft.  | 
$200  | 
 
Solar Hot Water  | 
N/A  | 
N/A  | 
ICS w/aux. elec.
                    tank  | 
$2400  | 
 
PV system  | 
N/A  | 
N/A  | 
3.25kW array  | 
$20,000  | 
 
Total Incremental Cost  | 
    | 
($854)  | 
    | 
$27,301  | 
 
 
Conclusions 
Through various programs that the federal government has initiated,
              the search for more affordable, energy efficient and sustainable
              temporary housing is taking a more aggressive stance in the building
              environment.  When FSEC was tasked by DOE to develop a proposal
              for improved specifications for FEMA, we sought input from various
              industry partners to discuss different ways to improve the current
              FEMA specifications.  This included manufactured home building
              personnel, material manufacturers, building science researchers
              and others.  FEMA personnel was contacted on numerous occasions
              but declined to comment.  These discussions along with several
              published reports formed the basis for the proposed recommendations
              in this report.  One such published report was a site visit
              conducted by a member of the Building America Industrialized Housing
              Partnership and others affiliated with manufactured housing industry
              in September of 2004.  The report discloses possible moisture-related
              problem areas and made recommendations for manufactured homes built
              for FEMA and destined for Hurricane Charley victims.  The
              largest problem areas were the vapor barrier placement, duct leakage
              and oversized hvac systems (Chasar, et. al. 2004).  In July
              of 2000 the first HUD-Code home made of structural insulated panels
              (SIPS) was tested, instrumented and monitored for energy efficiency
              (Baechler, et al., 2002).  The results of this experiment
              provided the premise from which the BASIP was developed.  
The FEMA procured manufactured
              homes are currently constructed in accordance with the Housing
              and Urban Development’s   manufactured housing standards
              (the HUD code).  While there are many examples of high quality
              and cost effective manufactured homes, the  FEMA minimum standard
              homes can consume more energy than their site built comparatives
              and use materials and mechanical systems that can potentially contribute
              to poor indoor quality and low durability. Two improved specifications
              are presented in this report to enhance energy efficiency, sustainability,
              indoor air quality and provide back up power, without compensating
              human health, safety or comfort, for high performance ruggedized
              temporary housing.   
Imagine the headlines
              revised from “The Land of 10,770 Empty FEMA Trailers” (Figure
              11), to “10,770 Zero Energy Trailers Provide Power for Small
              Community”.  If these units had been built with the BASIP specifications,
              they could generate enough power to provide basic power necessities
              of a small parish.  With more and more headlines like “FEMA
              Homes Stranded in NC”,  “Thousands
              Still Waiting for FEMA Trailers”;
              how does FEMA justify the process for temporary housing?  Placing
              manufactured homes into communities affected by natural disasters,
              such as Hurricane Katrina has met enormous resistance by neighboring
              communities, as well as, local officials.  “The NIMBY
              (not in my backyard) effect goes beyond the Big Easy itself: Half
              of Louisiana's parishes have banned new trailer parks”.  The
              Punta Gorda FEMA Park (largest-ever trailer park) has received
              accusations about drug dealing, domestic abuse, theft and vandalism.  Despite
              those concerns, some believe extraordinary events require extraordinary
              cooperation.  
  
Figure 11. More than 10,000 trailers were sitting
              at the airport in Hope, AR  
            (AP Photo by Danny Johnston)  
The proposed specifications still need further investigation with
              regards to code exceptions and/or exemptions and fire resistance
              compliance due to innovative technologies that have evolved since
              the development and implementation of the HUD Code.  Space
              planning and overall layout should also be examined further.  While
              this report does not explore floor plan redesign at this time,
              it does identify a few designs that have evolved since Hurricane
              Katrina left so many victims homeless.  Hurricane Katrina
              brought about many design charettes and discussions by architects,
              developers, politicians and manufactured housing executives.  We
              can even look historically at measures taken after the San Francisco
              earthquake of 1906 left thousands homeless and over 5,600 “temporary
              cottages” were built (see Figure 12). 
  
The
              consensus is that affordable, temporary housing needs to take on
              a new shape and mission.  The U.S Department of Energy's Office
              of Energy Efficiency and Renewable Energy Department’s
              annual Solar Decathlon, a competition to design, build, and operate
              the most attractive and energy-efficient solar-powered home, displays
              examples every year of self sufficient innovative homes, that have
              been transported to the Mall in Washington D.C.   Regardless,
              Hurricane Katrina has proved that a new process and strategy is
              in need, one that is healthy, sustainable, and reusable and before
              an energy crisis hits home again, and one that is energy efficient
              and responsible. 
References 
- Code of Federal Regulations Housing and Urban Development [HUD],
                Manufactured Home Construction and Safety Standards, 24, Part
                3280, US Government Printing Office, 1999.
 
- Baechler, M.; Lubliner, M; Gordon, A (2002). “Pushing
                the Envelope: A Case Study of Building the First Manufactured
                Home Using Structural Insulated Panels” Proceedings of
                ACEEE 2002 Summer Study, American Council for an Energy Efficiency
                Economy, Pacific Grove, CA.
 
- Chasar, D., Moyer, N., McIlvaine, J., Beal, D. and Chandra,
                S., "Energy Star Manufactured Homes: The Plant Certification
                Process," Proceedings of ACEEE 2004 Summer Study, American
                Council for an Energy Efficient Economy, Washington, DC, August
                2004.
 
- Harrison, J., Tiedeman, T. “Solar Water Heating Options
                in Florida”, Florida Solar Energy Center, Cocoa, FL, FSEC-EN-9,
                May 1997
 
- McGinley, W. M., “Study of Innovative Manufactured Housing
                Envelope Materials”, Final Report to the Florida Solar
                Energy Center, Under the Building America Industrialized Housing
                Partnership, April 2002.
 
- Moyer, N., Beal, D., Chasar, D., McIlvaine, J., Withers, C.,
                and Chandra, S., “Moisture Problems in Manufactured Housing:
                Probable Causes and Cures,”  Proceedings of ASHRAE
                Conference IAQ2001, American Society of Heating, Refrigerating
                and Air-Conditioning Engineers, Inc., Atlanta, GA,   August
                2001.
 
- Parker, D. et al, 1999. "Energy Gauge® USA: A Residential
                Building Energy Simulation Design Tool", Proceedings of
                Building Simulation ’99. International Building Performance
                Simulation Association, Organizing Committee for the 6th International
                IBPSA Conference, Department of Architecture Texas A&M University,
                TX. 
 
 
Acknowledgement 
This work is sponsored,
              in large part, by the US Department of Energy (DOE), Office of
              Energy Efficiency and Renewable Energy, Building Technologies Program
              under cooperative agreement number DE-FC26-99GO10478. This support
              does not constitute an endorsement by DOE of the views expressed
              in this report. 
The authors appreciate
              the encouragement and support from Bert Kessler (Palm Harbor Homes),
              Bill Wachtler (Structural Insulated Panel Association), Bill Chaleff
              (Chaleff  & Rogers, Architects), Janet McIlvaine (Florida Solar
              Energy Center), Danny Parker (Florida Solar Energy Center), Eric
              Martin (Florida Solar Energy Center), Dennis Stroer (Calcs Plus),
              Michael Lubliner (Washington State University), Michael Baechler
              (Pacific Northwest National Laboratory), Mike Dalton (Polyfoam),
              Ron Sparkman (Barvista Homes), John Michael (ATEX Distributing).  |